  "id": "prj-lahore-wastewater-drainage-management",
  "recordType": "infrastructureProject",
  "name": "Lahore Wastewater and Drainage Management Project",
  "projectType": "sewerage",
  "institutionIds": [
    "ins-wasa-lahore",
    "ins-punjab-water-sanitation-authority"
  ],
  "networkIds": [
    "net-wasa-lahore-sewerage",
    "net-wasa-lahore-stormwater-drainage"
  ],
  "assetIds": [
    "ias-wasa-lahore-trunk-sewer-line-a",
    "ias-wasa-lahore-trunk-sewer-line-b",
    "ias-wasa-lahore-trunk-sewer-line-c",
    "ias-wasa-lahore-gulshan-ravi-ultimate-disposal-station"
  ],
  "territoryPlaceIds": [
    "plc-pk-punjab-lahore-wasa-service-area"
  ],
  "status": "procurement",
  "statusAsOf": "2026-08-02",
  "schedule": {
    "plannedStart": "2026-01-01",
    "plannedEnd": "2030-12-31",
    "expectedClose": "2031-06-30"
  },
  "funding": [
    {
      "funder": "Asian Infrastructure Investment Bank",
      "amount": 160,
      "currency": "USD million",
      "fundingStatus": "approved"
    },
    {
      "funder": "Government of the Punjab",
      "amount": 17,
      "currency": "USD million equivalent",
      "fundingStatus": "approved"
    }
  ],
  "scope": [
    "Construct three trunk sewers with a combined planned length of 32.37 kilometres.",
    "Construct a new pumping station with 16 pumps.",
    "Rehabilitate about 7 kilometres of surface drains.",
    "Divert sewage so nearly 9 kilometres of local surface drains can be freed from wastewater discharge.",
    "Install 450 kilowatts of solar support at the planned Gulshan-e-Ravi disposal station.",
    "Close or eliminate selected intermediate pumping and disposal stations after the new system operates."
  ],
  "evidenceState": "verified",
  "citations": [
    "cit-aiib-lahore-project-scope",
    "cit-aiib-lahore-project-finance-schedule",
    "cit-aiib-lahore-esia-alignments",
    "cit-wasa-lahore-current-procurement"
  ],
  "lastCheckedDate": "2026-08-02",
  "reviewState": "reviewed",
  "notes": "AIIB financing is approved. The public WASA register shows technical tender evaluation, but no checked contract award or notice to proceed. The model therefore says procurement, not construction."
}